Posted: Tuesday, 12 November 2013 3:00PM

After Refueling Cook's Unit 2 Returns To Service



A refueling outage has gone off without a hitch at the Cook Nuclear Plant. Each unit is scheduled to be refueled every 18-months. Communications Manager Bill Schalk says this go-around was a bit different, as large-scale Life Cycle Management projects were being done during the outage. These included replacement of two Feedwater Heaters.

Listen:

   
To complete the projects 1,900 contracted workers were brought in to help the regular 1,200-person plant staff. Unit 2 outage began October 2 and returned to operation Tuesday morning. The next unit to be refueled is Unit 1, which will be next fall.

   